We visited the site on Friday afternoon and the windows were on, frame stage should have been completed on Friday and we have a site meeting with our SS on Monday. Also received the invoice by email from the accounts department on the same day!. Boy they are quick in sending invoices...been waiting for the revised final working drawings for a month and still haven't received it yet!.
Front View of house
Cloak room window on right and study room windows on the left.
Study, lounge and dinning room windows
View from back of house.
Ground floor windows are in but 1st floor has not been installed yet.
Dining room windows and opening for Bi fold doors
Theater room windows on left and family room windows on right.
We will probably drop by again before Monday and take some photo's of the 1st floor windows.
Hey Pups, It's looking Great!! they put our scaffolding up after the windows were put in so when i went around and saw some out i was thinking "oh no they have broke some!" but all it was was they took them out so the scaffolding clamping didn't interfere...You'll be roof tiled and wrapped in no time!
ReplyDeleteTell me, did you guys get extra insulation on the ground floor walls and in between floors?
Hi Mel,
ReplyDeleteWe got free insulation for the walls due to the 5star rating :)
We didn't get any between floors though, we are using the blue underlay so hopefully that will help.
How about you did you add the insulation for the walls and between floors? how much did it cost?