Thursday, 28 July 2011

plastering started

Our place is at the plastering stage, we had our preplaster inspection a few weeks back and met with our SS for reinspection to go over all the defects which had been rectified before the sheets where put up. So far our SS has been great, very organised and takes pride in his work.

Our 1st floor bricks were cleaned on Tuesday, and our Bi fold doors has been delivered. Official lock up should be this week, will have to drop by tomorrow to check.






wall insulation batts where up on 9th July and ceiling batts where up on 23rd July.













Study room











Sheets up on 26th July.










Kitchen with wider fridge space option










Our bi-fold doors on site 27th July.

2 comments:

  1. brilliant pupps!!! looking very good...i didn't know there was a wider fridge space option, good thinking 99.

    i have been very lazy in updating our blog...we've just completed lockup too and plastering is to start this week (was supposed to be last week but we had a few hiccups which i won't go into here).

    really coming along and its very exciting!

    cheers,

    m

    ReplyDelete
  2. thanks Mel, I thought that the original fridge space was not big enough for those french door fridge designs. Although it took some space from the galley and the walk in pantry :(

    I can't believe that we are at fixing stage already and things seems to be moving fast :). I am getting lazy to update my blog too but I just have to do it.

    hope your build goes well too!

    ReplyDelete